Blog Layout

The CanExel products at a glance

Name Length Nominal Width Nominal Thickness Weight
Ced’R-Vue™ 6” Snap Lap 12’ (3,66 m) 6” (15.24cm) 3/8 (9.53 mm) 2 lb per sq. ft.
Ced’R-Vue™ 9” Lap 12’ (3,66 m) 9” (22.86 cm) 3/8 (9.53 mm) 2 lb per sq. ft.
Ridgewood D-5™ 12’ (3,66 m) 12” (30.48 cm) 7/16 (11.11 mm) 2 lb per sq. ft.
UltraPlank™ 12’ (3,66 m) 12” (30.48 cm) 7/16 (11.11 mm) 2 lb per sq. ft.
These installation instructions are in accordance with the standards of the National Building Code of Canada, section 9.27, and are intended to cover the normal building practices encountered in Canada and the United States.

Installation guide:

Stud spacing

1. Can be installed over both sheathed and unsheathed walls.


2. Must be nailed into studs spaced not more than 16 inches. 


3. Siding should not come in direct contact with concrete and must maintain a minimum gap of eight inches between the bottom edge of the siding and the ground.


4. Siding may be applied over masonry constructions as long as furring strips are utilized and securely attached to masonry assembly on 16-inch centers. 

Moisture

1. Check local building codes for moisture handling application procedures.


2. Gutters are recommended for controlled roof water runoff.


3. Basement and crawl spaces should be sealed with a layer of polythene, asphalt, or polythene to minimize the risk of moisture damage.


4. Siding must not be applied to green or crooked structural framing members.


5. Do not apply siding over rains-soaked or buckled sheathed materials.


6. A vapor barrier with less than 1 perm rating must be installed on the warm side or the interior surface of the wall. It should be further extended behind partition walls to form continuous protection of exterior walls.


7. Consult local building code for a secondary weather-resistant barrier. 

Flashing windows and door openings

1. All openings must be properly sealed/flashed to prevent moisture buildup.


2. Siding applied adjacent to walks, porches, patios, must have a 2” clearance above any surface.


3. Forcing or springing siding into place will cause buckling.


4. Leave a 3/16-inch gap whenever siding butts against anything. 

Kick-out flashing

1. Install step flashing with a minimum 4-inch upper leg.


2. Do not extend the siding or trim into the kick-out flashing gutter.


3. Maintain clearance between gutter end and adjoining walls.

Insulated sheathing

1. Whether it’s low-compression rigid foam or fiberglass, adequate bracing of the wall is in accordance with the National Building Code.


2. Siding can be nailed directly on rigid foam sheathing up to 1” thick unless the local building code demands a drainage plane. Nail length must be increased to ensure a minimum 1-1/4“ fastener penetration into structural framing.


3. In the case of fiberglass or rigid foam sheathing more than 1”, a minimum of 1-1/4“ thick by 4” wide strapping must be installed over the sheathing. The strapping must be securely fastened to structural framing spaced no greater than 16” OC. The minimum nail penetration should be 1-1/4 inches and the maximum nail spacing should not exceed the width of the siding.



If you're interested in getting premium facade design and installation for your siding project, get in touch with Vancouver Facade today.

Blog

HardiePlank Siding on House
By Riley Speers 29 Jan, 2022
Check Out The Pros and Cons of Using HardiePlank Siding on Your Home or Building. Vancouver Facade is a high-end siding contractor located in Vancouver, B.C.
Aluminum Siding Panels on House
By Riley Speers 29 Jan, 2022
If your aluminum siding is looking dirty and you're curious as to how to clean it, read this article! Vancouver Facade is a premium siding contractor based in Vancouver, B.C. We offer high-end custom siding design and construction services.
Live Edge Wood Siding on Building
By Riley Speers 29 Jan, 2022
Are you curious about how wood siding is actually installed on a building? Check out the steps required to install wood siding materials on your next project. Vancouver Facade is a siding contractor located in Vancouver, B.C. offering commercial siding installation.
More Posts
Share by: